STATE SECRETARY FOR THE RUSSIAN PROTECTOR IN THINGS AND IN MORAVA, PRAGUE, inv. 2522, sig. 109-12/169

Page 15

English Translation

110 to be able to detect and fix the central heating system, a test heating will be carried out on 30 March. The new parquets will be laid in the dining room after completion of the painting work. The repair work on the exterior facade is ongoing. The completion of all masonry work is to be expected until April 15th and the interior work including planned air protection measures until April 21st. The gardener's apartment can be purchased on April 3rd. On behalf of: gez.: Mittmeyer Certified: Aneer BOLLE 113 70158