STÁTNÍ TAJEMNÍK U ŘÍŠSKÉHO PROTEKTORA V ČECHÁCH A NA MORAVĚ, PRAHA, inv. 1647, sig. 109-4/1402 (poškozeno) Page 21 · 21 of 22
STATE SECRETARY FOR THE RUSSIAN PROTECTOR IN THINGS AND IN MORAVA, PRAGUE, inv. 1647, sig. 109-4/1402 (damaged)
English Translation
8 Installation. For the construction of the warehouse in Prague-Veitsberg are still needed: 15 bricklayers 420 000 bricks 25 auxiliary workers 950 dz lime 12 deep graves 640 m sawn wood and within 4 weeks still: incl. 150 m2Balconies 18 carpenters and 5 m roundwood 25 auxiliary workers For the warehouse in Schwemmau: 25 bricklayers 260 000 bricks 60 auxiliary workers 302 m2 Šchnittholz 500 dz lime For the storage hall in Brno: 12 bricklayer 8 carpenters 45 construction assistants 5 other workers Pür the warehouse at Mähr.-Ostrau is required the same number of workers as for the storage room in Brno. For the warehouses in Brno and Moravian-Ostrava: 570 000 bricks 604 m Šchnittholz 1 000 dz lime. The authorised representative for the regulation of the construction industry The authorized representative for dic Prague to present the 17 July 1943 construction industry to the Reichsprotector in Bohemia and Moravia. L Mr. State Secretary. The construction of the 6 potato warehouses is to be carried out with Prot GB XvIII k 3 by